.


:




:

































 

 

 

 


. 3




. . .

, - . . , , 50%, 1 .

, .

50% (Tracking).

.

- . .

. , .

, , - 02.04.08 (Sat 02.04.08).

. . .

100% .

4.

, , , . , . - ,

, , , , .

.

(View* Tracking Gantt). .

1. .

2. , , , .

3. .

: .

: , , , .

1. .

2. .

3. .

4. .

5. .

6. .

7. .

 

 

8

: , .

: MS Project

:

. , , .

, , , . , , , , , , , , . , . .

: , , , .

Ø (Project ♦ Project Information). (Project Information). (Start date) (Finish date) .

Ø (Statistics). (Project Statistics). (Current) (Baseline) . (Actual) . (Variance) . (Start) (Finish) . (Duration), (Work) (Cost) , . (Duration) (Work) (Percent complete) .

Ø (Close), (Project Statistics).

.

Ø (View ♦ Reports). (Reports).

Ø (Overview)

Ø (Select). (Overview Reports).

Ø (Project Summary).

Ø (Select). .

Ø , .

. . (Dates) . (Start), . (Baseline Start), , (Actual Start) , . (Finish), . (Baseline Finish), , (Actual Finish) , . . (Start Variance) . (Finish Variance) .

(Duration) . (Work) , (Costs) - . (Scheduled) , (Baseline) - . (Actual) , (Variance) - . (Remaining) , , (Percent Complete) - .

(Task Status) . (Tasks not yet started) , , (Tasks in progress) - . (Tasks completed) , (Total Tasks) - .

(Resource Status) . (Work Resources) , , . (Overallocated WorkResources) - . (Material Resources) , (Total Resources) - . , 6 5 .

(Print).

Ø (Close), .

Ø (Reports) (Close). (Reports) .

.

: , , , .

.

Ø (View ♦ Reports). (Reports).

Ø (Overview).

Ø (Select). (Overview Reports).

Ø (Top-Level Tasks).

Ø (Select). .

(Task Name) , (Duration) - . (Start) , (Finish) - . % (Percent Complete) , (Costs) - . (Print).

Ø (Qose), .

.

Ø (Reports) , (Overview).

Ø (Select). (Overview Reports).

Ø (Milestones).

Ø (Select). .

(Task Name) , (Duration) - , 0. (Start) , (Finish) - .

Ø (Close), . .

Ø (Reports) , (Overview).

Ø (Select). (Overview Reports).

Ø (Working Days).

Ø (Select). .

. , - (Standard). .

Ø . .

.

, , .

Ø (Close), .

Ø (Reports) (Close). (Reports) .

.

,
: , , .

, .

Ø (View ♦ Reports). (Reports).

Ø (Current Activities).

Ø (Select). (Current Activity Reports).

Ø (Completed Tasks).

Ø (Select). .

. () , (Task Name) - , (Duration) - . (Start) , (Finish) - . % (Percent .) , (Cost) - .

, .

Ø . .

Ø (Work) .

Ø , .

Ø (Close), .

, .

Ø (Reports) (Current Activities).

Ø (Select). (Current Activity Reports).

Ø , (Tasks Starting Soon).

Ø (Select). (Date Range).

Ø , (Show tasks that start or finish after) 01.02.05, .

Ø OK, (Date Range). (Date Range).

. () , . (Task Name) . (Duration) , (Start) - , (Finish) - .

Ø (Close), .

.

Ø (Reports) (Current Activities).

Ø (Select). (Current Activity Reports).

Ø (Tasks In Progress).

Ø (Select). , . , .

Ø , .

Ø (Reports) (Close). (Reports) .

.

: , , .

.

Ø (View ♦ Reports). (Reports).

Ø (Costs).

Ø (Select). (Cost Reports).

Ø (Cash Flow).

Ø (Select). .

Ø . .

Ø . .

Ø . .

(Total) .

(Close), .

.

Ø (Reports) (Costs).

Ø (Select). (Cost Reports).

Ø (Budget).

Ø (Select). .

. () , (Task Name) - . (Fixed Cost) , , (Fixed Cost Accrual) - .

Ø . .

(Total Cost)- , (Baseline) - , (Actual) - , (Variance) - .

Ø (Close), . .

Ø (Reports) (Costs).

Ø (Select). (Cost Reports).

Ø (Over-budget Tasks).

Ø (Select). .

, . . , .

Ø . .

, 10,44.

Ø (Close), .

.

Ø (Reports) (Costs).

Ø (Select). (Cost Reports). '

Ø (Over-budget Resources).

Ø (Select). .

. , .

Ø (Close), .

Ø (Reports) (Close). (Reports) .

.

, .

Ø (View ♦ Reports). (Reports).

Ø (Assignments).

Ø (Select). (Assignment Reports).

Ø (Who Does What).

Ø (Select). , .

. () . (Resource Name) . (Overtime Work) , (Work) - .

Ø (Close), , .

, .

Ø (Reports) (Assignments).

Ø (Select). (Assignment Reports).

Ø (Who Does What When).

Ø (Select). , .

. . . , .

Ø (Close), , .

, .

Ø (Reports) (Assignments).

Ø (Select). (Assignment Reports).

Ø ( Do List).

Ø (Select). (Using Resource).

Ø , (Show tasks using) .

Ø , (Using Resource). ,

. () , . (TaskName) , . (Duration) , (Start) - , (Finish) - .

Ø (Close), , .

, ,

.

Ø (Reports) (Workload).

Ø (Select). (Workload Reports).

Ø (Task Usage).

Ø (Select).

Ø (Close), .

, .

Ø (Reports ) (Workload).

Ø (Select). (Workload Reports).





:


: 2018-10-15; !; : 257 |


:

:

,
==> ...

1696 - | 1573 -


© 2015-2024 lektsii.org - -

: 0.112 .