. . .
, - . . , , 50%, 1 .
, .
50% (Tracking).
.
- . .
. , .
, , - 02.04.08 (Sat 02.04.08).
. . .
100% .
4.
, , , . , . - ,
, , , , .
.
♦ (View* Tracking Gantt). .
1. .
2. , , , .
3. .
: .
: , , , .
1. .
2. .
|
|
3. .
4. .
5. .
6. .
7. .
8
: , .
: MS Project
:
. , , .
, , , . , , , , , , , , . , . .
: , , , .
Ø ♦ (Project ♦ Project Information). (Project Information). (Start date) (Finish date) .
Ø (Statistics). (Project Statistics). (Current) (Baseline) . (Actual) . (Variance) . (Start) (Finish) . (Duration), (Work) (Cost) , . (Duration) (Work) (Percent complete) .
Ø (Close), (Project Statistics).
.
Ø ♦ (View ♦ Reports). (Reports).
Ø (Overview)
Ø (Select). (Overview Reports).
Ø (Project Summary).
Ø (Select). .
Ø , .
. . (Dates) . (Start), . (Baseline Start), , (Actual Start) , . (Finish), . (Baseline Finish), , (Actual Finish) , . . (Start Variance) . (Finish Variance) .
|
|
(Duration) . (Work) , (Costs) - . (Scheduled) , (Baseline) - . (Actual) , (Variance) - . (Remaining) , , (Percent Complete) - .
(Task Status) . (Tasks not yet started) , , (Tasks in progress) - . (Tasks completed) , (Total Tasks) - .
(Resource Status) . (Work Resources) , , . (Overallocated WorkResources) - . (Material Resources) , (Total Resources) - . , 6 5 .
(Print).
Ø (Close), .
Ø (Reports) (Close). (Reports) .
.
: , , , .
.
Ø ♦ (View ♦ Reports). (Reports).
Ø (Overview).
Ø (Select). (Overview Reports).
Ø (Top-Level Tasks).
Ø (Select). .
(Task Name) , (Duration) - . (Start) , (Finish) - . % (Percent Complete) , (Costs) - . (Print).
Ø (Qose), .
.
Ø (Reports) , (Overview).
|
|
Ø (Select). (Overview Reports).
Ø (Milestones).
Ø (Select). .
(Task Name) , (Duration) - , 0. (Start) , (Finish) - .
Ø (Close), . .
Ø (Reports) , (Overview).
Ø (Select). (Overview Reports).
Ø (Working Days).
Ø (Select). .
. , - (Standard). .
Ø . .
.
, , .
Ø (Close), .
Ø (Reports) (Close). (Reports) .
.
,
: , , .
, .
Ø ♦ (View ♦ Reports). (Reports).
Ø (Current Activities).
Ø (Select). (Current Activity Reports).
Ø (Completed Tasks).
Ø (Select). .
. () , (Task Name) - , (Duration) - . (Start) , (Finish) - . % (Percent .) , (Cost) - .
, .
Ø . .
Ø (Work) .
Ø , .
Ø (Close), .
, .
Ø (Reports) (Current Activities).
Ø (Select). (Current Activity Reports).
|
|
Ø , (Tasks Starting Soon).
Ø (Select). (Date Range).
Ø , (Show tasks that start or finish after) 01.02.05, .
Ø OK, (Date Range). (Date Range).
. () , . (Task Name) . (Duration) , (Start) - , (Finish) - .
Ø (Close), .
.
Ø (Reports) (Current Activities).
Ø (Select). (Current Activity Reports).
Ø (Tasks In Progress).
Ø (Select). , . , .
Ø , .
Ø (Reports) (Close). (Reports) .
.
: , , .
.
Ø ♦ (View ♦ Reports). (Reports).
Ø (Costs).
Ø (Select). (Cost Reports).
Ø (Cash Flow).
Ø (Select). .
Ø . .
Ø . .
Ø . .
(Total) .
(Close), .
.
Ø (Reports) (Costs).
Ø (Select). (Cost Reports).
Ø (Budget).
Ø (Select). .
. () , (Task Name) - . (Fixed Cost) , , (Fixed Cost Accrual) - .
Ø . .
(Total Cost)- , (Baseline) - , (Actual) - , (Variance) - .
Ø (Close), . .
Ø (Reports) (Costs).
Ø (Select). (Cost Reports).
Ø (Over-budget Tasks).
Ø (Select). .
, . . , .
|
|
Ø . .
, 10,44.
Ø (Close), .
.
Ø (Reports) (Costs).
Ø (Select). (Cost Reports). '
Ø (Over-budget Resources).
Ø (Select). .
. , .
Ø (Close), .
Ø (Reports) (Close). (Reports) .
.
, .
Ø ♦ (View ♦ Reports). (Reports).
Ø (Assignments).
Ø (Select). (Assignment Reports).
Ø (Who Does What).
Ø (Select). , .
. () . (Resource Name) . (Overtime Work) , (Work) - .
Ø (Close), , .
, .
Ø (Reports) (Assignments).
Ø (Select). (Assignment Reports).
Ø (Who Does What When).
Ø (Select). , .
. . . , .
Ø (Close), , .
, .
Ø (Reports) (Assignments).
Ø (Select). (Assignment Reports).
Ø ( Do List).
Ø (Select). (Using Resource).
Ø , (Show tasks using) .
Ø , (Using Resource). ,
. () , . (TaskName) , . (Duration) , (Start) - , (Finish) - .
Ø (Close), , .
, ,
.
Ø (Reports) (Workload).
Ø (Select). (Workload Reports).
Ø (Task Usage).
Ø (Select).
Ø (Close), .
, .
Ø (Reports ) (Workload).
Ø (Select). (Workload Reports).