, (Task Information).

(Advanced).

(Task type) ,
(Fixed Duration), .

(Duration) 3 .

(Resources)

200%.

- , (TaskInformation).

- (Advanced).

- (Task type) ,
(Fixed Units),
.

. . . MS Project .

.

- -

-

-

, (Resource) , (Task) - , . (Work) , (Units) - , .

- (Work contour) (Back Loaded), .

- , (Assign
ment Information).
, .

- , ,

.

-
, (Assignment Information) (General)

- (Start) 24 2008 .

- (Finish)
3 2008 .

.

- (Notes) (Notes). , .

. , , .

.

(Task Usage)
(View ♦ Resource
Graph). .

, - . , - . , , - .

. . .

- ♦ ♦ (Format ♦
Details ♦ Work). , ..

- ♦ ♦ (Format ♦ Details ♦ Cumulative Work). , .. .

- ♦ ♦ (Format ♦Details ♦ Percent Allocation). , ..
.

- ♦ ♦ (Format ♦ Details ♦ Cost). , .. .

- ♦ ♦

(Format ♦ Details ♦ Peak Units), .

, , 2008. , , - . .