MS Project . → (Tools → Options). , , . (Set as default), , .
2 (View).
. 2
(Default view) , . , , . , .
(Date format) .
(Show) , .
(General) ( 3) . Microsoft Project (Genera option for Microsoft Office Project) , (General options for) . (Planning Wizard) , .
. (Prompt for project info for new projects) .
. 3
MS Project (AutoFilter), . (Formatting) , (Set AutoFilter for new projects) .
(Automatically add new resources and tasks). .
(Edit) ( 4) ( ), , , ( ) .
(Allow cell drag and drop) , , (Move selection after enter) , Enter. (Edit directly to cell) , . , .
|
|
. 4
(Ask to update automatic links) , . . .
(Add space before label) , . , .
( 5) , . . .
.
, , .
, .
. 5
, . . . .
( 6) , . , , , , , .
- , . , . , , .
. 6
- , . .
.
|
|
. , . .
.
.
.
. , - . . .
.
.
.
. , - . , . :
;
;
.
(Show scheduling messages) , MS Project .
2.
MS Project.
, , , . , . , .
MS Project , . MS Project 1 2.
. 1
(Baseline) | |
(Constraint Dates) | ( ) |
(Cost) | |
(Delay) | |
(Earned Value) | , |
(Earned Value Schedule Indicators) | |
(Earned Value Cost Indicators) | |
(Enter) | |
(Export) | |
(Hyperlink) | , |
(PA_Expected Case) (PA_Optimistic Case) (PA_Pessimistic Case) | PERT. , |
PERT (PA_PERT Entry Sheet) | , PERT |
(Rollup Table) | |
Schedule ( ) | , |
(Summary) | |
(Tracking) | |
(Usage) | , , , |
(Variance) | |
(Work) |
|
|
. 2
(Cost) | |
(Earned Value) | |
(Entry) | |
(Entry Material Resources) | |
(Entry Work Resources) | |
(Export) | |
(Hyperlink) | , Internet Intranet |
(Summary) | |
(Usage) | , |
(Work) | , |
, , , (Gantt Chart). , . , .
→ (View→Table). → . , (More tables).
3.
. . , , , ..
. , , , , . : (tasks), (resource) (assignment).
, . , , . .
, . , . . MS Project (summary task). , .
|
|
. , .
, , . MS Project (milestone). , , . , , , , , 0 , . , .
- , . . (duration) , , (work) , .
, , , . (dependencies) (links). - , , .
, . , , , . . , , , , , .
(cost) . MS Project : (rate) (cost per use). . . , , . , . , .
, . , , . , . :
- ;
- , , , , ;
- , ;
- , , , , .
, . , , , , . , , , . , , , , . , . , . . , .
|
|
. , , . , . , , , , , . . , .
4. MS Project
, . , MS Project, .
, . , . , ( ). , , .
, , .
() MS Project , (New) . , (Project Information) ( 7). , → (Project→Project Information).
7
: . , : , , . , : , , .
(Schedule from).
(Start date) (Finish date). .
(Current date) (Status date). , (NA). . , .
, , . , , MS Project , , .
, (Calendar) . MS Project , , . :
1) (Standard);
2) 24 (24 Hours);
3) (Night shift).
8 , , .
. . MS Project ( ), . . , , . .
0 1000, . , .
.
. .
( ) . , , . , , .
. , , . , . , . , .
. . .
(Gantt Chart). [2] , . (Task name). , , .
, , , . , .
, (Þ) Alt+Shift+. (Ü) Alt+Shift+.
8.
8
8 .
, . , . , , , 0 ( 9).
9
, , . , , ( 10).
10
, 0, , 0. . , ( 11).
11
.
, (Duration). .
, 1 . (?). , (estimated) . , , . , , , ( 12).
12
, . , , .
, , (Predecessor), , , (Successor). , , .
. . .
MS Project .
1) (Finish to Start), (FS). , , . :
2) (Start to Start), (SS), , , . , . :
3) - (Finish to Finish), (FF) , , . , , , . , , , .
4) - (Start to Finish), (SF). , , , .
, ( - ). , , , ( ) ( 13).
13
( 14).
14
(Type) , (Lag) . (Delete) .